3. The MPS planner at Murphy Motors uses MPS time-phased records for planning end-item production. The planner
Question:
3. The MPS planner at Murphy Motors uses MPS time-phased records for planning end-item production.
The planner is currently working on a schedule for the P24, one of Murphy’s top-selling motors. The planner uses a production lot size of 70 and a safety stock of 5 for the P24 motor.
On Week Item: P24 hand 1 2 3 4 5 6 7 8 Forecast 30 30 30 40 40 40 45 45 Orders 13 8 4 Projected available balance 20 Available-to-promise MPS
a. Complete the MPS time-phased record for product P24.
b. Can Murphy accept the following orders? Update the MPS time-phased record for accepted orders.
Order Amount Desired Week 1 40 4 2 30 6 3 30 2 4 25 3
Step by Step Answer:
Manufacturing Planning And Control For Supply Chain Management
ISBN: 9780073377827
6th Edition
Authors: F. Robert Jacobs, William Berry, David Clay Whybark, Thomas Vollmann