Question:

5. A metal fabricating company has the following master production schedule for one of its items

(a frame), as well as the accompanying product structure.

Week 1 Week 2 Week 3 Week 4 MPS 20 30 35 20 The resource profile for the frame is as follows:

Item Work Center Setup Hours Run Hours/Unit Lead Time Frame 200 4 1.5 0 weeks Part A 300 3 1.0 1 week Part B 300 3 .8 1 week Part C 400 2 1.2 2 weeks Part D 500 2 1.0 1 week Determine the capacity requirements for all work centers, assuming all usages are one, and that a new setup is required in each week at each work center.

Frame Part A Part C Part D Part B 268 Chapter 7 Capacity Planning and Management

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Manufacturing Planning And Control For Supply Chain Management

ISBN: 9780073377827

6th Edition

Authors: F. Robert Jacobs, William Berry, David Clay Whybark, Thomas Vollmann

Question Posted: