8. The following input-output data were gathered at the end of week 8 for a work center:
Week 1 2 3 4 5 6 7 8 Planned input 60 60 60 60 60 60 60 60 Actual input 68 70 75 70 68 60 55 55 Planned output 65 65 65 65 65 65 65 65 Actual output 60 62 63 63 64 65 63 60 Beginning backlog = 50 hours.
a. Complete the input/output document.
b. What was the planned objective?
c. Was it met?
d. What recommendations would you make?