9. The Optima Shop has two work centers: Big Mess and No Problem. The Monday list of orders to be filled this week shows the total setup and total run time requirements (in hours) at the two centers.

Joe Biggs, the scheduler of Optima, said his first criterion is to minimize setups, and the second is to prioritize customer orders in numerical order.

a. How should he schedule part production in the two centers? (Please illustrate using a Gantt chart.)