c. Fishers assembly foreman has just handed you the MRP records for the toy cup and plastic
Question:
c. Fisher’s assembly foreman has just handed you the MRP records for the toy cup and plastic molding material in Exhibit B. These MRP records contain a different master schedule, changed on-hand inventory values, and a new scheduled receipt value. Also, planned lead EXHIBIT B Material Requirements Planning Worksheet Week Number End Products 1 2 3 4 5 6 7 8 Game A master schedule 22 21 15 Game B master schedule 9 1 7 7 3 10 1 2 Toy Cup 1 2 3 4 5 6 7 8 Gross requirements
(2 units/game A)
(1 unit/game B)
Scheduled receipts*
Projected available balance 55 Planned order release
(Lead time = 2 weeks)
Plastic Molding Material 1 2 3 4 5 6 7 8 Gross requirements
(2 oz./toy cup)
Scheduled receipts* 166 Projected available balance 10 Planned order release
(Lead time = 2 weeks)
*Received at the beginning of each week.
238 Chapter 6A Advanced MRP time for both items is now two weeks. Complete the new MRP records for both items, assuming the part period balancing ordering policy is used for the toy cup and plastic material.