Consider a company facing a demand pattern and costs as follows: Month Sequential Number Requirements (Units) January
Question:
Consider a company facing a demand pattern and costs as follows:
Month Sequential Number Requirements (Units)
January 1 350 February 2 200 March 3 0 April 4 150 May 5 500 June 6 600 July 7 450 August 8 350 September 9 200 October 10 0 November 11 150 December 12 200 Total 3,150 A $50.00 r (per month) 0.02$/$/month v $65.00
a. Construct a replenishment schedule and calculate the associated costs using the fixed EOQ method.
b. Repeat using the Wagner–Whitin algorithm.
c. Repeat using the Silver–Meal heuristic.
d. Repeat using the LUC method.
e. Repeat using the PPB method.
f. Repeat using the POQ method.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Inventory And Production Management In Supply Chains
ISBN: 9781032179322
4th Edition
Authors: Edward A Silver, David F Pyke, Douglas J Thomas
Question Posted: