In a chase strategy, if planned production for the month is 10,000 units and employee productivity is
Question:
In a chase strategy, if planned production for the month is 10,000 units and employee productivity is 85 units per month, how many employees should the firm employ at the beginning of the month?
a. 115
c. 118
b. 120
d. 125