In a situation where the main source of uncertainty is due to timing of customer orders, which
Question:
In a situation where the main source of uncertainty is due to timing of customer orders, which buffering strategy would be expected to perform best?
a. Safety stock
b. Safety lead time
c. Scrap allowance
d. All of the above would perform about the same