In a well-functioning material requirements planning (MRP) system, what percent of parts would be expected to require

Question:

In a well-functioning material requirements planning (MRP) system, what percent of parts would be expected to require planner review (via exception codes) in any given processing cycle?

a. 1–5%

b. 5–10%

c. 10–20%

d. 20–30%