One key to avoiding an overstated master production schedule (MPS) is to a. Force the MPS to
Question:
One key to avoiding an overstated master production schedule (MPS) is to
a. Force the MPS to match the production plan (in terms of total units)
b. Always maintain a positive available-to-promise (ATP) balance
c. Always maintain a negative available-to-promise (ATP) balance
d. Freeze the MPS for at least four weeks