One key to avoiding an overstated master production schedule (MPS) is to a. Force the MPS to

Question:

One key to avoiding an overstated master production schedule (MPS) is to

a. Force the MPS to match the production plan (in terms of total units)

b. Always maintain a positive available-to-promise (ATP) balance

c. Always maintain a negative available-to-promise (ATP) balance

d. Freeze the MPS for at least four weeks