The path traveled by containers in a two-container kanban system is a. Inbound inventorysupply centerfinal assembly areaoutbound
Question:
The path traveled by containers in a two-container kanban system is
a. Inbound inventory—supply center—final assembly area—outbound inventory
b. Supply center—inbound inventory—final assembly area—outbound inventory
c. Supply center—outbound inventory—inbound inventory—final assembly area
d. Outbound inventory—inbound inventory—supply center—final assembly area
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Manufacturing Planning And Control For Supply Chain Management
ISBN: 9780071750318,9780071750325
1st Edition
Authors: F. Robert Jacobs, William Lee Berry, D. Clay Whybark, Thomas E. Vollmann
Question Posted: