Using cumulative available-to-promise (ATP) logic, calculate the master production schedule (MPS) for the following conditions. How many
Question:
Using cumulative available-to-promise (ATP) logic, calculate the master production schedule (MPS) for the following conditions. How many units are available-topromise in period 2?
a. 20
b. 27
c. 45
d. 58