When manufacturing lead times exceed customer requirements and products can be constructed from modular components, which master
Question:
When manufacturing lead times exceed customer requirements and products can be constructed from modular components, which master production scheduling (MPS)
approach is most likely to be employed?
a. Make-to-order
b. Assemble-to-order
c. Make-to-stock
d. Engineer-to-order