Question:

1. The project manager for a construction project discovers that the local city council may change the building code to allow adjoining properties to combine their sewage systems.

She knows that a competitor is about to break ground in the adjacent lot and contacts him to discuss the possibility of having both projects save costs by building a sewage system for the two projects.

This is an example of which strategy?

Mitigate Share Accept Exploit