1. Tom is a project manager for a software company. He is contracting a long-term software project...

Question:

1. Tom is a project manager for a software company. He is contracting a long-term software project with an external company. That company charges him $20/hour per employee and $300 overhead per month. What kind of contract is he using?

FP CPPC CR T&M