1. You're managing a project, when your client tells you that an external problem happened, and now...
Question:
1. You're managing a project, when your client tells you that an external problem happened, and now you have to meet an earlier deadline. Your supervisor heard that in a situation like this, you can use schedule compression by either crashing or fast-tracking the schedule, but he's not sure which is which. What do you tell him? A. Crashing the project adds risk, while fast-tracking adds cost. B. When you crash a project, it always shortens the total duration of the project C. Crashing the project adds cost, while fast-tracking adds risk. D. When you fast-track a project, it always shortens the total duration of the project