1. You're managing a project, when your client tells you that an external problem happened, and now...

Question:

1. You're managing a project, when your client tells you that an external problem happened, and now you have to meet an earlier deadline. Your supervisor heard that in a situation like this, you can use schedule compression by either crashing or fast-tracking the schedule, but he's not sure which is which. What do you tell him? A. Crashing the project adds risk, while fast-tracking adds cost. B. When you crash a project, it always shortens the total duration of the project C. Crashing the project adds cost, while fast-tracking adds risk. D. When you fast-track a project, it always shortens the total duration of the project

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Head First PMP

ISBN: 9781449364915

3rd Edition

Authors: Jennifer Greene, Andrew Stellman

Question Posted: