10. One of your team members has discovered a defect in a deliverable and has recommended that...
Question:
10. One of your team members has discovered a defect in a deliverable and has recommended that it be repaired. Which of the following is NOT true: A The project charter has authorized you to perform the work B. Your project is in Monitor and Control Project Work process C. The defect repair must be approved before the deliverable can be repaired D. You must update the project management plan to document the defect