12. You are the project manager for a software project, when the sponsor pulls the plug and...

Question:

12. You are the project manager for a software project, when the sponsor pulls the plug and cancels the project. What do you do? A. Give the team the day off to recuperate from the bad news B. Create a budget summary for the remaining unspent budget C. Create the closure procedures and update the organizational process assets D. Find new assignments for any people previously assigned to your project