12. You are working on a construction project that is running slightly behind schedule. You ask the...

Question:

12. You are working on a construction project that is running slightly behind schedule. You ask the team to put in a few extra hours on their shifts over the next few weeks to make up the time. To make sure everyone feels motivated to do the extra work, you set up a $1,500 bonus for everyone on the team who works the extra hours if the deadline is met. What kind of power are you using? A. Legitimate B. Reward C. Expert D. Referent