14. What's the correct order of the Time Management planning processes? A. Activity Sequencing, Activity Definition, Activity

Question:

14. What's the correct order of the Time Management planning processes? A. Activity Sequencing, Activity Definition, Activity Resource Estimating, Activity Duration Estimating, Schedule Development B. Activity Definition, Activity Sequencing, Schedule Development, Activity Resource Estimating, Activity Duration Estimating C. Activity Definition, Activity Sequencing, Activity Resource Estimating, Activity Duration Estimating, Schedule Development D. Schedule Development, Activity Definition, Activity Sequencing, Activity Resource Estimating, Activity Duration Estimating