14. You are managing an industrial architecture project. You've spent $26,410 so far to survey the site,
Question:
14. You are managing an industrial architecture project. You've spent $26,410 so far to survey the site, draw up preliminary plans, and run engineering simulations. You are preparing to meet with your sponsor, when you discover that there a new local zoning law will cause you to have to spend an additional estimated $15,000 to revise your plans. You contact the sponsor and initiate a change request to update the cost baseline. What variable would you use to represent the $26,410 in an Earned Value calculation? A. PV B. BAC C. AC D. EV
Step by Step Answer:
Related Book For
Question Posted: