15. You are working on the project plan for a software project. Your company has a standard...

Question:

15. You are working on the project plan for a software project. Your company has a standard spreadsheet that you use to generate estimates. To use the spreadsheet, you meet with the team to estimate the number of functional requirements, use cases and design wireframes for the project. Then you categorize them into high, medium or low complexity. You enter all of those numbers into the spreadsheet, which uses a data table derived from past projects' actual costs and durations, performs a set of calculations, and generates a final estimate. What kind of estimation is being done? A. Parametric B. Rough order of magnitude C. Bottom-up D. Analogous

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Head First PMP

ISBN: 9781449364915

3rd Edition

Authors: Jennifer Greene, Andrew Stellman

Question Posted: