16. Project A has a NPV of $75,000, with an internal rate of return of 1.5% and...

Question:

16. Project A has a NPV of $75,000, with an internal rate of return of 1.5% and an initial investment of $15,000. Project B has a NPV of $60,000 with a BCR of 2:1. Project C has a NPV of $80,000, which includes an opportunity cost of $35,000. Based on these projects, which is the BEST one to select: A. Project A B. Project B C. Project C D. There is not enough information to select a project