Question:

16. You’re managing a project to remodel a kitchen. You find out from your supplier that there’s a 50% chance that the model of oven that you planned to use may be discontinued, and you’ll have to go with one that costs $650 more. What’s the EMV of that risk?

$650

–$650

$325

–$325