16. You're working on a project schedule network diagram, and you need to decide on either the...

Question:

16. You're working on a project schedule network diagram, and you need to decide on either the arrow diagramming method or precedence diagramming method. Which of the following is NOT true? A. PDM has activities on arrows, while ADM has activities on nodes B. ADM uses dummy activities with zero duration to add paths to the network C. Both ADM and PDM diagrams can be used in critical path analysis D. PDM can show different kinds of dependencies, while ADM can only show finish-to-start (FS) dependencies

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Head First PMP

ISBN: 9781449364915

3rd Edition

Authors: Jennifer Greene, Andrew Stellman

Question Posted: