18. A construction project manager has a meeting with the team foreman, who tells him that theres...
Question:
18. A construction project manager has a meeting with the team foreman, who tells him that there’s a good chance that a general strike will delay the project. They brainstorm to try to find a way to handle it, but in the end decide that if there’s a strike, there is no useful way to minimize the impact to the project. This is an example of which risk response strategy?
Mitigate Avoid Transfer Accept