18. A construction project manager has a meeting with the team foreman, who tells him that theres...

Question:

18. A construction project manager has a meeting with the team foreman, who tells him that there’s a good chance that a general strike will delay the project. They brainstorm to try to find a way to handle it, but in the end decide that if there’s a strike, there is no useful way to minimize the impact to the project. This is an example of which risk response strategy?

Mitigate Avoid Transfer Accept

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Head First PMP

ISBN: 9781449364915

3rd Edition

Authors: Jennifer Greene, Andrew Stellman

Question Posted: