18. You are managing a software project, when one of your stakeholders needs to make a change...

Question:

18. You are managing a software project, when one of your stakeholders needs to make a change that will affect the budget. What defines the processes that you must follow in order to implement the change? A Cost change control system B. Monitoring & Controlling process group C. Change control board D. Cost baseline