19. Youre managing a project to fulfill a military contract. Your project team is assembled, and work

Question:

19. You’re managing a project to fulfill a military contract. Your project team is assembled, and work has begun. Your government project officer informs you that a supplier that you depend on has lost the contract to supply a critical part. You consult your risk register and discover that you did not plan for this. What’s the BEST way to handle this situation?

Consult the probability and impact matrix Perform quantitative and qualitative risk analysis Recommend preventive actions Look for a new supplier for the part