22. You are a project manager working on a project. Your sponsor wants to know who a...

Question:

22. You are a project manager working on a project. Your sponsor wants to know who a certain work package is assigned to, what control account to bill it against, and what work is involved. What document do you refer her to? A Scope Management Plan B. WBS C. WBS Dictionary D. Scope Statement

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Head First PMP

ISBN: 9781449364915

3rd Edition

Authors: Jennifer Greene, Andrew Stellman

Question Posted: