22. You're planning the schedule for a highway construction project, but the final date you came up...
Question:
22. You're planning the schedule for a highway construction project, but the final date you came up with will run into the next budget year. The state comes up with capital from a reserve fund, and now you can increase the budget for your resources. What's the BEST way to compress the schedule? A Go back to your three-point estimates and use the most optimistic ones B. Use the extra budget to increase your contingency reserve C. Hire more experts to use expert judgment so your estimates are more accurate. D. Crash the schedule