24. You're managing a construction project. You've decomposed work packages into activities, and your client needs a
Question:
24. You're managing a construction project. You've decomposed work packages into activities, and your client needs a duration estimate for each activity that you came up with. Which of he following will you use for this? A. Activity sequencing B. Resource calendar C. Critical path analysis D. Milestone list