3. Which of the following is NOT TRUE about a work breakdown structure? A. It describes processes...
Question:
3. Which of the following is NOT TRUE about a work breakdown structure? A. It describes processes to define the scope, verify work, and manage scope changes. B. It contains a graphical, hierarchical list of all work to be performed C. It can be broken down by project phase or deliverable D. It is an important element of the scope baseline