3. You take a look at the number of defects you have found in your project per...
Question:
3. You take a look at the number of defects you have found in your project per phase and find that it is higher in your project than it has been in most other projects that the company is doing. You dig a little deeper and find some previously unplanned risks that have been causing trouble on your project.
Reassessment Audit Technical Performance Measurement Trend Analysis Reserve Analysis