3. You take over for a project manager who has left the company and realize that team...

Question:

3. You take over for a project manager who has left the company and realize that team is talking directly to the customer and only having status meetings when there are problems. The programming team has one idea about the goals of the project, and the testing team has another. Which document is the FIRST one that you should create to solve this problem? A. Communication plan B. Status report C. Meeting agenda D. Performance report