4. You are working on a project with a PV of $56,733 and an SPI of 1.2....
Question:
4. You are working on a project with a PV of $56,733 and an SPI of 1.2. What's the Eamed Value of your project? A. $68,079.60 B. $47,277.50 C. $68,733 D. .72
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For