5. You are managing a software project. Your team has been working for eight weeks, and so...
Question:
5. You are managing a software project. Your team has been working for eight weeks, and so far the project is on track. The lead programmer comes to you with a problem: there is a work package that is causing trouble. Nobody seems to know who is responsible for it, the accounting department does not know what cost center to bill it against, and it's not even clear exactly what work should be performed. Which of the following would BEST help this situation? A. Alternatives Analysis B. WBS Dictionary C. Scope Management Plan D. Scope Verification