5. You’re managing a construction project. There’s a 30% chance that weather will cause a three-day delay, costing $12,000. There’s also a 20% chance that the price of your building materials will drop, which will save $5,000. What’s the total EMV for both of these?
–$3,600
$1,000
–$2,600
$4,600