Question:
5. You're managing an industrial design project. You created a communication plan, and now the team is working on the project. You've been communicating with your team, and now you're looking at the work performance information to evaluate the performance of the project. Which of the following BEST describes the next thing you should do? A. Use formal written communication to inform the client of the project status B. Compare the work performance information against the time, cost and scope baselines and look for deviations C. Update the organizational process assets with your lessons learned D. Hold a status meeting