6. Joe is the project manager of a large software project. When its time to identify risks...

Question:

6. Joe is the project manager of a large software project. When it’s time to identify risks on his project, he contacts a team of experts and has them all come up with a list and send it in anonymously. What technique is Joe using?

SWOT Ishikawa diagramming Delphi Brainstorming