7. Three members of your project team want to pad their estimates because they believe there are...

Question:

7. Three members of your project team want to pad their estimates because they believe there are certain risks that might materialize. What is the BEST way to handle this situation? A. Estimate the activities honestly, and then use a contingency reserve to cover any unexpected costs B. Allow more time for the work by adding a buffer to every activity in the schedule C. Tell the team members not to worry about it, and if the schedule is wrong it's okay for the project to be late D. Crash the schedule