7. You are working on a project with an SPI of .72 and a CPI of 1.1.
Question:
7. You are working on a project with an SPI of .72 and a CPI of 1.1. Which of the following BEST describes your project? A. Your project is ahead of schedule and under budget B. Your project is behind schedule and over budget C. Your project is behind schedule and under budget D. Your project is ahead of schedule and over budget