8. Which of the following is NOT true about the triple constraint? A. The project manager needs...

Question:

8. Which of the following is NOT true about the triple constraint? A. The project manager needs to pay attention to all three constraints. B. You can increase quality by increasing scope. C. A change in one of the three constraints often leads to a change in the other two. D. Any change in time, cost, or scope can potentially affect quality.