8. Your project has a BAC of $4,522 and is 13% complete. What is the earned value...

Question:

8. Your project has a BAC of $4,522 and is 13% complete. What is the earned value (EV)? A $3934.14 B. There is not enough information to answer C. $587.86 D. $4522