8. You're managing a highway construction project. The foreman of your building team alerts you to a

Question:

8. You're managing a highway construction project. The foreman of your building team alerts you to a problem that the inspection team found with one of the pylons, so you use an Ishikawa diagram to try to figure out the root cause of the defect. What process is being performed? A. Quality Management B. Quality Planning C. Perform Quality Control D. Perform Quality Assurance