9. You are starting to write your preliminary scope statement with your project sponsor when the senior

Question:

9. You are starting to write your preliminary scope statement with your project sponsor when the senior managers ask for a time and cost estimate for the project. You have not yet gathered many of the project details. What kind of estimate can you give? A. Analogous Estimate B. Rough Order of Magnitude Estimate C. Parametric Estimate D. Bottom-up Estimate