An intelligent node of a distributed control system has four tasks, 1 4 (rate
Question:
An intelligent node of a distributed control system has four tasks, τ1 – τ4 (rate - monotonic priorities), with the corresponding execution periods p1 = 10 ms, p2 = 100 ms, p3 = 500 ms, and p4 = 1000 ms. The execution times are e1 = 2 ms, e2 = 15 ms, e3 = 100 ms, and e4 = 10 ms, respectively.
However, task τ 1 is a critical control loop, whose execution period affects directly to the achievable control performance. Hence, in principle, that execution period should be as short as possible. What is the minimum execution period for τ1( = p1,min), if the maximum allowed CPU utilization factor is 0.91 ( “ dangerous ” )?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Real Time Systems Design And Analysis
ISBN: 9780470768648
4th Edition
Authors: Phillip A. Laplante, Seppo J. Ovaska
Question Posted: