An intelligent node of a distributed control system has four tasks, 1 4 (rate

Question:

An intelligent node of a distributed control system has four tasks, τ1 – τ4 (rate - monotonic priorities), with the corresponding execution periods p1 = 10 ms, p2 = 100 ms, p3 = 500 ms, and p4 = 1000 ms. The execution times are e1 = 2 ms, e2 = 15 ms, e3 = 100 ms, and e4 = 10 ms, respectively.

However, task τ 1 is a critical control loop, whose execution period affects directly to the achievable control performance. Hence, in principle, that execution period should be as short as possible. What is the minimum execution period for τ1( = p1,min), if the maximum allowed CPU utilization factor is 0.91 ( “ dangerous ” )?