Using the data in the table from the previous problem: a. Create a table similar to the

Question:

Using the data in the table from the previous problem:

a. Create a table similar to the one in Figure 3.27 if you haven’t done so already.

b. For Week 4, calculate the budget at completion (BAC), planned value (PV), actual cost (AC), and earned value (EV) at week 3.

c. For Week 4, calculate the performance measures of cost variance (CV), schedule variance (SV), the cost performance index (CPI), and the schedule performance index (SPI).

d. What can you say about the budget in Week 4 by using these performance measures?

e. What can you say about the schedule in Week 4 by using these performance measures?

f. For Week 4, calculate the estimated time to complete (ETC) and estimate at completion (EAC).

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Systems Analysis And Design

ISBN: 9780273787105

9th Global Edition

Authors: Kenneth Kendall, Julie Kendall

Question Posted: