Verify the schedulability under rate - monotonic algorithm and construct the schedule of the following task set:
Question:
Verify the schedulability under rate - monotonic algorithm and construct the schedule of the following task set: τ1 ≡ {3, 7}, τ2 ≡ {5, 16}, and τ3 ≡ {3, 15}. Here, the notation τi ≡ {ei , pi} gives the execution time, ei , and period, pi , of task τi .