On a 1000-MVA common base, a two-area system interconnected by a tie line has the following parameters:

Question:

On a 1000-MVA common base, a two-area system interconnected by a tie line has the following parameters:

image text in transcribed

The two areas are operating in parallel at the nominal frequency of \(60 \mathrm{~Hz}\). The areas are initially operating in steady state with each area supplying 1000 MW when a sudden load change of \(187.5 \mathrm{MW}\) occurs in area 1. Compute the new steady-state frequency and change in tie-line power flow

(a) without LFC, and

(b) with LFC.