A builder agreed to build 78 houses in eight months at a fixed price. Due to bad

Question:

A builder agreed to build 78 houses in eight months at a fixed price. Due to bad weather conditions and unexpected labor shortages, the work took 22 months and cost $107,000 more than anticipated.

Discuss the extent to which builders can use poor weather and labor shortages as unforeseen events and a defence for the recovery of $107,000.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: